Pass4Test 는 완전히 여러분이 인증시험 준비와 안전한 시험패스를 위한 완벽한 IASSC ICYB (IASSC Certified Lean Six Sigma Yellow Belt)덤프제공 사이트입니다.우리 Pass4Test의 덤프들은 응시자에 따라 ,시험 ,시험방법에 따라  알 맞춤한 퍼펙트한 자료입니다.여러분은 Pass4Test의 알맞춤 덤프들로 아주 간단하고 편하게  인증시험을 패스할 수 있습니다.많은  it인증관연 응시자들은  우리 Pass4Test가 제공하는 문제와 답으로 되어있는 IASSC ICYB (IASSC Certified Lean Six Sigma Yellow Belt) 덤프로 자격증을 취득하셨습니다.우리 Pass4Test 또한 업계에서 아주 좋은 이미지를 가지고 있습니다.

 

 

 

 

NO.1 The ROI for a project is a measurement metric that stands for Return on Investment and is one

of

the methods used to measure the success of a Lean Six Sigma project.

A. True

B. False

Answer: A

 

NO.2 Training cost is $3,000 and a project required an initial investment of $12,000. If the project

yields

monthly savings of $1,800 beginning after 3 months, what is the payback period in months (before

money costs and taxes)?

A. 4.17

B. 8.33

C. 11.33

D. 28.28

Answer: C

 

NO.3 Six Sigma refers to a process whose output has at least 95% of its data points within 6

Standard

Deviations from the Mean.

A. True

B. False

Answer: B

 

NO.4 When a process has proven itself to function at a Six Sigma level this means there are less than

________ defects per million opportunities.

A. 1.7

B. 2.6

C. 3.4

D. 10

Answer: C

 

NO.5 In the expression Y = f(Xn) Y , the output, is the ___________ variable and Xn, the inputs, are

the

__________ variables.

A. Independent, dependent

B. Individual, multiple

C. Sole, multiple

D. Dependent, independent

Answer: D

 

NO.6 When we assess the Voice of the Customer we are attempting to determine the gaps in our

processes between “what is” and __________________.

A. “What isn’t”

B. “What will make money”

C. “What will cost less”

D. “What should be”

Answer: D

 

NO.7 The DMAIC approach to problem solving stands for Define, __________, Analyze, Improve and

Control.

A. Manage

B. Measure

C. Memorize

D. Manipulate

Answer: B

 

NO.8 Benefits and working conditions would be primarily the concern of which of the following?

A. Voice of the Customer

B. Voice of the Employee

C. Voice of the Business

D. Voice of the Process

Answer: B

 

NO.9 Which of the following would likely not be a CTQ (Critical-to-Quality) for the purchase of a

product?

A. Functionality

B. Durability

C. Dependability

D. None

Answer: D

 

NO.10 Voice of the Customer is a Lean Six Sigma technique to determine the ___________ attributes

of

a product or service.

A. Desirable

B. Beneficial

C. Critical-to-Quality

D. Preferred

Answer: C

 

 