우리 Pass4Test에서는 최고이자 최신의 IASSC ICYB (IASSC Certified Lean Six Sigma Yellow Belt)덤프자료를 제공 함으로 여러분을 도와 IASSC ICYB (IASSC Certified Lean Six Sigma Yellow Belt)인증자격증을 쉽게 취득할 수 있게 해드립니다.만약 아직도 IASS C IC YB (IASSC Certified Lean Six Sigma Yellow Belt)시험패스를 위하여 고군분투하고 있다면 바로 우리 Pass4Test를 선택함으로 여러분의 고민을 날려버릴수 있습니다.
NO.1 When a process has proven itself to function at a Six Sigma level this means there are less than
________ defects per million opportunities.
A. 1.7
B. 2.6
C. 3.4
D. 10
Answer: C
NO.2 Training cost is $3,000 and a project required an initial investment of $12,000. If the project
yields
monthly savings of $1,800 beginning after 3 months, what is the payback period in months (before
money costs and taxes)?
A. 4.17
B. 8.33
C. 11.33
D. 28.28
Answer: C
NO.3 Which of the following would likely not be a CTQ (Critical-to-Quality) for the purchase of a
product?
A. Functionality
B. Durability
C. Dependability
D. None
Answer: D
NO.4 The DMAIC approach to problem solving stands for Define, __________, Analyze, Improve and
Control.
A. Manage
B. Measure
C. Memorize
D. Manipulate
Answer: B
NO.5 Benefits and working conditions would be primarily the concern of which of the following?
A. Voice of the Customer
B. Voice of the Employee
C. Voice of the Business
D. Voice of the Process
Answer: B
NO.6 The ROI for a project is a measurement metric that stands for Return on Investment and is one
of
the methods used to measure the success of a Lean Six Sigma project.
A. True
B. False
Answer: A
NO.7 When we assess the Voice of the Customer we are attempting to determine the gaps in our
processes between “what is” and __________________.
A. “What isn’t”
B. “What will make money”
C. “What will cost less”
D. “What should be”
Answer: D
NO.8 Voice of the Customer is a Lean Six Sigma technique to determine the ___________ attributes
of
a product or service.
A. Desirable
B. Beneficial
C. Critical-to-Quality
D. Preferred
Answer: C
NO.9 Six Sigma refers to a process whose output has at least 95% of its data points within 6
Standard
Deviations from the Mean.
A. True
B. False
Answer: B
NO.10 In the expression Y = f(Xn) Y , the output, is the ___________ variable and Xn, the inputs, are
the
__________ variables.
A. Independent, dependent
B. Individual, multiple
C. Sole, multiple
D. Dependent, independent
Answer: D