IASSC ICGB (IASSC Certified Lean Six Sigma Green Belt)시험을 어떻게 패스할가 고민그만하고 Pass4Test의 IASSC ICGB (IASSC Certified Lean Six Sigma Green Belt)시험대비 덤프를 데려가 주세요.가격이 착한데 비해 너무나 훌륭한 IASSC ICGB (IASSC Certified Lean Six Sigma Green Belt) 덤프품질과 높은 적중율, Pass4Test가 아닌 다른곳에서 찾아볼수 없는 혜택입니다.
NO.1 A Lean Principle that addresses efficiency by the process worker is called
____________________?
A. Visual Factory
B. Supervising
C. Training
D. Standardizing
Answer: D
NO.2 When it comes to Control one of the most effective means of eliminating defects is to
_________________ .
A. Train personnel often and thoroughly
B. Keep a Six Sigma project going on the process at all times
C. Design defect prevention into the product
D. Have each process consist of no more than five steps
Answer: C
NO.3 The Lean Principle action in the 5S approach that deals with having those items needed
regularly
at hand and those items need less regularly stored out of the way is known as ___________.
A. Shining
B. Standardizing
C. Sustaining
D. Sorting
Answer: D
NO.4 As part of a Visual Factory plan __________ cards are created and utilized to identify areas in
need of cleaning and organization.
A. Kanban
B. Kaizen
C. Poke-Yoke
D. WhoSai
Answer: A
NO.5 Significant variation in process performance is a consequence of several causes that can be
classified using which of the terminologies shown. (Note: There are 2 correct answers).
A. Common
B. Random
C. Uneducated
D. Special
E. Vital
Answer: A,D
NO.6 SPC on the outputs is more preferred than SPC on the inputs when implementing SPC for your
process.
A. True
B. False
Answer: B
NO.7 The use of Kanbans work best with pull systems for determining the timing of which products
or
services are produced.
A. True
B. False
Answer: A
NO.8 While management of a company must set the stage for all improvement efforts, which of
these
5S’s is primarily driven by management?
A. Straighten
B. Sort
C. Shine
D. Sustain
Answer: D
NO.9 The use of station warning lights, tool boards and jidohka devices in the application of Lean
accomplish which of these principles?
A. Pilferage Minimization
B. Visual Factory
C. Management Awareness
D. Operator Attentiveness
Answer: B
NO.10 When a Belt applies the practice of Poka-Yoke to a project challenge she is attempting to make
certain the activity is _______________ .
A. Well documented
B. Removed from the line
C. Mistake proofed
D. Highly visible
Answer: C
IASSC ICGB (IASSC Certified Lean Six Sigma Green Belt)덤프자료보기
Posted 2013/6/1 5:57:57 | Category: 미분류 | Tag: