NO.1 Who carries out audits that are independent of the project?

A. Quality
assurance

B. Project Assurance

C. Project Support

D. Project
Manager

Answer: A



NO.2 What process is used by the Project Board to
respond to an Exception Report?

A. Controlling a Stage

B. Managing a Stage
Boundary

C. Managing Product Delivery

D. Directing a Project

Answer:
D



NO.3 Which statement defines a risk?

A. A certain event occurring in
the future that will have a negative impact on the project's objectives

B. An
event that has already occurred that the Project Manager must deal with
immediately

C. An uncertain event, or set of events that, should it or they
occur, will have an effect on the

achievement of objectives

D. An
uncertain event, or set of events that, should it or they occur, will be
automatically escalated

to the Project Board for a response

Answer:
C



NO.4 Which of the following is NOT part of quality planning?

A.
Define quality responsibilities

B. Gain acceptance of the project
product

C. Agree acceptance criteria

D. Set quality tolerances

Answer:
B



NO.5 Which is assumed to be a supplier's responsibility in the PRINCE2
customer/supplier

environment?

A. Specify the desired result

B. Provide
the resources and skills to deliver the desired result

C. Pay for the
project

D. Specify the benefits of the project

Answer: B



NO.6 Why
is a Project Brief produced?

A. To act as a trigger for the Starting up a
Project process

B. To record the strategies and management controls to be
used by a project

C. To provide a full and firm foundation for the initiation
of a project

D. To be used by the Project Board as a basis for reviewing the
progress of a project

Answer: C



NO.7 Which statement is FALSE?

A. A
project outcome perceived to be negative by one or more stakeholders is a
dis-benefit

B. A project's output is any of the project's specialist
products

C. A project benefit is only realized after the project has
closed

D. A project outcome is the result of the change derived from using
the project's outputs

Answer: C



NO.8 In what
product should the quality criteria for a specialist product be recorded?


A.
Quality Management Strategy

B. Quality Register

C. Product
Description

D. Project Product Description

Answer: C