IASSC ICBB (IASSC Certified Lean Six Sigma Black Belt) 시험이 너무 어려워 보여서 오르지못할 산처럼 보이시나요? 그건 Pass4Test의 IASSC ICBB (IASSC Certified Lean Six Sigma Black Belt) 시험문제에 대비하여 제작한 IASSC ICBB (IASSC Certified Lean Six Sigma Black Belt) 덤프가 있다는 것을 모르고 있기때문입니다.IASSC ICBB (IASSC Certified Lean Six Sigma Black Belt) 시험에 도전하고 싶으시다면 최강 시험패스율로 유명한 Pass4Test의 IASSC ICBB (IASSC Certified Lean Six Sigma Black Belt) 덤프로 시험공부를 해보세요.시간절약은 물론이고 가격도 착해서 간단한 시험패스에 딱 좋은 선택입니다.
NO.1 Control Charts were developed by Dr. Shewhart to track data over time. To detect Special
Cause
variation the Control Charts use which of these?
A. Data shift analysis
B. Outlier analysis methods
C. Center Line and Control Limits
D. None of the above
Answer: C
NO.2 Common and ______________ Cause Variation are the focus of Statistical Process Control.
A. Uncommon
B. Ordinary
C. Special
D. Selective
Answer: C
NO.3 Range Charts are the technique used to determine if Special Causes are occurring within the
subgroups of the ______________.
A. Histograms
B. SPC Charts
C. NP Charts
D. Pareto Charts
Answer: B
NO.4 Special Cause Variation falls into which two categories?
A. Natural & Unnatural
B. Short Term & Long Term
C. Assignable & Pattern
D. Attribute & Discreet
Answer: C
NO.5 Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for
the
process?
A. Xbar Chart
B. Time Series Chart
C. Neither
D. Both
Answer: A
NO.6 When a Belt Poka-Yoke’s a defect out of the process entirely then she should track the activity
with a robust SPC system on the characteristic of interest in the defect as an early warning
system.
A. True
B. False
Answer: B
NO.7 A ___________ is used primarily to track the stability of the average value of a metric of
interest.
A. NP Chart
B. Xbar-R Chart
C. I-MR Chart
D. C Chart
Answer: B
NO.8 For her injection molding project a Belt needed to track the percentage of defectives of a
particular
sample set so she used a ___________ to display the data?
A. Individual Chart
B. C Chart
C. Xbar Chart
D. P Chart
Answer: D
NO.9 Following the completion of a LSS project the Belt not only creates a Control Plan he also
develops a _____________ so those involved in the process know what to do when the critical
metrics move out of spec.
A. Response Plan
B. Call List
C. Chain-of-Command
D. Defect Analysis Plan
Answer: A
NO.10 If the production is for higher volume and monitoring and the Mean and variability is to be
monitored for four machines producing product and the characteristic to be monitored is Variable
Data, which SPC Chart is best to be selected?
A. Xbar-R Chart
B. Individual-MR Chart
C. NP Chart
D. CUSUM Chart
Answer: A
IASSC ICBB (IASSC Certified Lean Six Sigma Black Belt) 인증덤프공부
Posted 2013/6/1 5:55:33 | Category: 미분류 | Tag: