Pass4Test 에서 출시한   BCS Certification PRF덤프는   BCS Certification PRF실제시험의 출제범위와 출제유형을 대비하여 제작된 최신버전 덤프입니다. 시험문제가 바뀌면 제일 빠른 시일내에 덤프를 업데이트 하도록 최선을 다하고 있으며 1년 무료 업데이트서비스를 제공해드립니다. 1년 무료 업데이트서비스를 제공해드리기에 시험시간을 늦추어도  BCS Certification PRF시험성적에 아무런 페를 끼치지 않습니다. Pass4Test에 믿음을 느낄수 있도록 구매사이트마다 무료샘플 다운가능기능을 설치하였습니다.무료샘플을 체험해보시고 Pass4Test을 선택해주세요.

 

NO.1 Which is a benefit of using PRINCE2?
A. Provides a defined structure of accountability, delegation, authority and communication
B. Includes techniques for critical path analysis and earned value analysis
C. Enables a Project Manager to be accountable for the success of a project
D. Prevents any changes once the scope of a project has been agreed
Answer: A

NO.2 What product identifies the management stages and other major control points in a project?
A. Business Case
B. Project Plan
C. Work Package
D. Project Brief
Answer: B

NO.3 What product forms the contract' between the Project Board and the Project Manager?
A. Project Brief
B. Project Initiation Documentation
C. Project mandate
D. Project Plan
Answer: B

NO.4 Which is a purpose of the Plans theme?
A. Identify, assess and control any potential changes to the baseline
B. Establish the project's structure of accountability
C. Assess and control uncertainty
D. Understand whether the targets are achievable
Answer: D

NO.5 Which role does NOT set tolerances?
A. Corporate or programme management
B. Project Board
C. Change Authority
D. Project Manager
Answer: C

NO.6 Identify the missing word(s) in the following sentence.
Following initiation, the Controlling a Stage process is used to manage and control each [ ? ] of a
project.
A. technical stage
B. benefit
C. management stage
D. Team Plan
Answer: C

NO.7 Why does PRINCE2 recommend three different levels of plans?
A. To cover initiation, specialist work and exception situations
B. To provide appropriate detail to each of the different levels of management within the project
C. As an allowance for initiation, product delivery and project closure
D. To match the different aspects of the product-based planning technique
Answer: B

NO.8 In which product would you find a product's quality tolerance defined?
A. Product Description
B. Quality Management Strategy
C. Quality Register
D. Configuration Item Record
Answer: A