NO.1 Which statement is FALSE?
A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
B. A project's output is any of the project's specialist products
C. A project benefit is only realized after the project has closed
D. A project outcome is the result of the change derived from using the project's outputs
Answer: C
NO.2 Which of the following is NOT part of quality planning?
A. Define quality responsibilities
B. Gain acceptance of the project product
C. Agree acceptance criteria
D. Set quality tolerances
Answer: B
NO.3 Which task is performed by the Change Authority?
A. Set a change budget
B. Approve or reject a request for change within approved limits
C. Refer changes that exceed budgetary limits to the Project Manager for approval
D. Update the configuration management system when a change is approved
Answer: B
NO.4 Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier
environment?
A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Pay for the project
D. Specify the benefits of the project
Answer: B
NO.5 In what product should the quality criteria for a specialist product be recorded?
A. Quality Management Strategy
B. Quality Register
C. Product Description
D. Project Product Description
Answer: C
NO.6 What is the first task of product-based planning?
A. Produce the Initiation Stage Plan
B. Write the Project Product Description
C. Identify dependencies
D. Create the product breakdown structure
Answer: B