Pass4Test의 PRINCE2 Certification PRINCE2시험덤프자료는 IT인사들의 많은 찬양을 받아왔습니다.이는 Pass4Test의 PRINCE2 Certification PRINCE2덤프가 신뢰성을 다시 한번 인증해주는것입니다.PRINCE2 Certification PRINCE2시험덤프의 인기는 이 시험과목이 얼마나 중요한지를 증명해줍니다. Pass4Test의 PRINCE2 Certification PRINCE2덤프로 이 중요한 IT인증시험을 준비하시면 우수한 성적으로 시험을 통과하여 인정받는 IT전문가로 될것입니다.

 

NO.1 According to PRINCE2, which of the following is a characteristic of a project compared to that

of business operations?

A. Incurs cost

B. Introduces business change

C. Delivers benefits

D. Creates products

Answer: B

 

NO.2 Identify the missing words in the following sentence... A PRINCE2 project is and controlled on

a stage-by-stage basis?

A. Planned, monitored

B. Developed, reported

C. Designed, assigned

D. Planned, produced

Answer: A

 

NO.3 According to PRINCE2, which of the following are the aspects of project performance to be

managed?

A. Processes, themes, principles

B. Time, cost, quality, people

C. Time, cost, quality

D. Time, cost, quality, scope, benefits, risk

Answer: D

 

NO.4 Which is a characteristic of a project?

A. Are risk free

B. Have no uncertainty

C. Are managed as part of business as usual

D. Are cross-functional

Answer: D

 

NO.5 Which is NOT a PRINCE2 integrated element?

A. The principles

B. The techniques

C. The themes

D. Tailoring PRINCE2 to the project environment

Answer: B

 

NO.6 Identify the missing word in the following sentence... A PRINCE2 project focuses on the

definition and delivery of, in particular their quality requirements?

A. Benefits

B. Products

C. Activities

D. Outcomes

Answer: B

 

NO.7 Which PRINCE2 principle supports planning only to a level of detail that is manageable and

foreseeable?

A. Continued business justification

B. Manage by exception

C. Focus on products

D. Manage by stages

Answer: D

 

NO.8 Which is a benefit of using PRINCE2?

A. Stakeholders are kept out of planning and decision making

B. Participants understand each other's roles and needs

C. Stakeholders are not involved in assuring the project work

D. All problems are escalated to all stakeholders

Answer: A

 