Microsoft Dynamics Sure Step MB5-705 (Managing Microsoft Dynamics Implementations) 시험을 패스하여 자격증을 취득하시면 찬란한 미래가 찾아올것입니다. Microsoft Dynamics Sure Step MB5-705 (Managing Microsoft Dynamics Implementations) 인증시험을 패스하여 취득한 자격증은 IT인사로서의 능력을 증명해주며 IT업계에 종사하는 일원으로서의 자존심입니다. Pass4Test 의 Microsoft Dynamics Sure Step MB5-705 (Managing Microsoft Dynamics Implementations) 덤프는 시험패스에 초점을 맞추어 제일 간단한 방법으로 시험을 패스하도록 밀어주는 시험공부가이드입니다.구매전 Microsoft Dynamics Sure Step MB5-705 (Managing Microsoft Dynamics Implementations) 무료샘플을 다운받아 적성에 맞는지 확인하고 구매할지 않할지 선택하시면 됩니다.
NO.1 Which document should you use to manage project deliverables?
A. project scope statement
B. project objectives
C. technical requirements
D. functional requirements
Answer: D
NO.2 You are a project manager. You are running a project by using the waterfall delivery method.
The project is in the development phase. Which Microsoft Dynamics Sure Step Methodology
supplemental documents are created to support the training?
A. performance test documents
B. data migration documents
C. user test documents
D. user guides
Answer: D
NO.3 You decide that a customer should be using the agile project type.
Which statement would cause you to make this decision?
A. The customer requirements are not fully defined, and the customer needs flexibility to
accommodate changing business priorities.
B. The customer requirements are clearly defined, and the customer needs flexibility to
accommodate changing business priorities.
C. The customer requirements are not fully defined, and the customer does not have changing
business priorities.
D. The customer requirements are clearly defined, and the customer does not have changing
business priorities.
Answer: A
NO.4 Which key document is a deliverable for the analysis phase of an agile project?
A. functional requirements document
B. Fit Gap Analysis
C. solution backlog
D. technical requirements document
Answer: C
NO.5 You are performing a Decision Accelerator Offering. In which order should you perform the
steps?
A. 1.Meet internally to discuss the Decision Accelerator Offering
2.Meet with the customer to discuss the Decision Accelerator Offering
3.Review the presentation and customer sign-off
4.Perform activities
B. 1.Meet with the customer to discuss the Decision Accelerator Offering
2.Meet internally to discuss the Decision Accelerator Offering
3.Perform activities
4.Review the presentation and customer sign-off
C. 1.Meet with the customer to discuss the Decision Accelerator Offering
2.Meet internally to discuss the Decision Accelerator Offering
3.Review the presentation and customer sign-off
4.Perform activities
D. 1.Meet internally to discuss the Decision Accelerator Offering
2.Meet with the customer to discuss the Decision Accelerator Offering
3.Perform activities
4.Review the presentation and customer sign-off
Answer: A
NO.6 Which two statements differentiating projects from operational work are correct? (Each
correct answer presents part of the solution. Choose two.)
A. The purpose of a project is to create a unique product, service, or result; the purpose of
operations is to sustain the customer's business.
B. The duration of a project is temporary; the duration of operational work is ongoing.
C. The output of a project is variable; the output of operational work is continuous, daily, and
predictable.
D. The purpose of a project is to sustain the new business requirements; operations end with the
adoption of a new set of objectives, and then the work continues.
E. a project ends when it is replaced by a new process; operations end when its specific objectives
have been attained.
Answer: A,B
NO.7 During your requirements and process review, you use the questionnaires provided by Sure
Step. What is one of the reasons that you use the questionnaire at this stage?
A. to assist in determining the budget of the project
B. to use as a tool by the partner prior to meeting with the customer
C. to create detailed process maps
D. to use as a checklist and a reminder of topics to investigate
Answer: D
NO.8 Which customer role is involved in the Fit Gap and Solution Blueprint Decision Accelerator?
A. project manager
B. key user
C. business decision maker
D. executive sponsor
Answer: C