NO.1 Which three statements are true? (Choose three.)
A. The Deliver operation copies change sets from the repository workspace to the flow target.
B. The Check-In operation copies files modified from the local sandbox to the repository workspace.
C. The Check-Out operation copies files from the repository workspace into the local sandbox.
D. The Accept operation copies change sets from the flow target into the repository workspace and
local sandbox.
Answer: A,B,D
NO.2 What is the velocity for a development team following the Scrum process template?
A. the average number of hours the team can deliver in an iteration
B. the average number of stories the team can deliver in an iteration
C. the average number of story points the team can deliver in an iteration
D. the average number of tasks the team can deliver in an iteration
Answer: C
NO.3 What are configurable items for the process template?
A. timelines, iterations, roles, and operational behaviors
B. plugins, cheat sheets, and dependencies
C. Java source code, source comments, and event handlers
D. categories, releases, and access control
Answer: A
NO.4 What is the main purpose of the work item discussion section?
A. to add notes and exchange information about the work item
B. to assign the owner of the work item
C. to move the work item through its lifecycle to the resolved state
D. to associate a work item with a release
Answer: A
NO.5 In an iteration plan, which value is represented by the length of the progress bar
A. The amount of work estimated
B. The amount of work completed
C. The amount of work on schedule
D. The amount of active work
Answer: B
NO.6 A team wants to make some attributes mandatory when work items are created. In order to
meet this objective, want can be done in Rational Team Concert ?
A. Work item attributes are all optional by design and there is no way to define mandatory
attributes for work items
B. Add a precondition to the Work Item Save operation to define which fields in a work item must
be filled in before it can be saved
C. Work item attributes are all mandatory by design. Users who create a work item are required to
fill in all the attributes.
D. Add a follow-up action to the Work Item Save operation to define the error message to display
when mandatory attributes are not filled in
Answer: B
NO.7 When does the RTC SCM detect conflicts? (Choose two.)
A. When incoming and outgoing change sets are coming from the same user
B. When incoming and outgoing change sets include changes to the same file
C. When incoming and outgoing change sets include changes to the same folders
D. When incoming and outgoing change sets are coming from two different users
Answer: B,C
NO.8 An organization uses the Formal Project Management process template for a project. Some
work items in the Gantt chart view of an iteration plan for the project are shown in red. What does
red indicate?
A. high severity
B. high priority
C. on the critical path
D. unassigned
Answer: C