ISQI Certifications CTFL-001시험을 패스하는 지름길은 Pass4Test에서 연구제작한 ISQI Certifica tions CTFL-001 험대비 덤프를 마련하여 충분한 시험준비를 하는것입니다. 덤프는 ISQI Certifica tions CTFL-001 험의 모든 범위가 포함되어 있어 시험적중율이 높습니다. ISQI Certifications CTFL-001시험패스는 바로 눈앞에 있습니다. 링크를 클릭하시고 Pass4Test의 ISQI Certifications CTFL-001시험대비 덤프를 장바구니에 담고 결제마친후 덤프를 받아 공부하는것입니다.
NO.1 Explain how the above mentioned report may differ from a report that you produce for the project
manager, who is a test specialist Select TWO items from the following options that can be used to report
to the project manager and would not be included in a report to senior management. 1 credit
A. Show details on effort spent
B. List of all outstanding defects with their priority and severity
C. Give product risk status
D. Show trend analysis
E. State recommendations for release
Answer: A,B
NO.2 As part of the improvement program, the organization is also looking at tool support. Which type of tool
could be used to ensure higher quality of the code to be reviewed? 1 credit
A. Review tool
B. Test execution tool
C. Static analysis tool
D. Test design tool
Answer: C
NO.3 Considerable attention will be given in this project to defining exit criteria and on reporting back on their
status. Which combination of TWO exit criteria from the list would be best to use? 1 credit
I. Total number of defects found
II. Percentage of test cases executed
III. Total test effort planned versus total actual test effort spent
IV. Defect trend (number of defects found per test run over time
A. (i) and (ii)
B. (i) and (iv)
C. (ii) and (iii)
D. (ii) and (iv)
Answer: D
NO.4 Since the system is in the medical domain and therefore in the safety critical area, testing needs to be
rigorous and evidence is required that the system has been adequately tested. Identify THREE measures
that would typically be part of the test approach in this domain and which are not always applicable in
other domains! 1 credit
A. High level of documentation
B. Failure Mode and Effect Analysis (FMEA) sessions
C. Traceability to requirements
D. Non-functional testing
E. Master test planning
F. Test design techniques
G. Reviews
Answer: A,B,C
NO.5 Identify the THREE types of formal peer reviews that can be recognized. 1 credit
A. Inspection
B. Management review
C. Walkthrough
D. Audit
E. Technical review
F. Informal review
G. Assessment
Answer: A,C,E
NO.6 You have been given responsibility for the non-functional testing of a safety-critical monitoring &
diagnostics package in the medical area. Which of the following would you least expect to see addressed
in the test plan? 1 credit
A. Availability
B. Safety
C. Portability
D. Reliability
Answer: C
NO.7 You are about to release a test progress report to a senior manager, who is not a test specialist. Which
of the following topics should NOT be included in the test progress report? 1 credit
A. Product risks which have been mitigated and those which are outstanding.
B. Recommendations for taking controlling actions
C. Status compared against the started exit criteria
D. Detailed overview of the risk-based test approach being used to ensure the exit criteria to be achieved
Answer: D
NO.8 A test log is one of the documents that need to be produced in this domain in order to provide evidence
of testing. However, the level of detail of test logs can vary. Which of the following is NOT an influencing
factor for the level of detail of the test logs being produced? 1 credit
A. Level of test execution automation
B. Test level
C. Regulatory requirements
D. Experience level of testers
Answer: D
NO.9 Consider the typical objectives of testing. Which of the following metrics can be used to measure the
effectiveness of the testing process in achieving one of those objectives? 1 credit
A. Average number of days between defect discovery and resolution
B. Percentage of requirements covered
C. Lines of code written per developer per day
D. Percentage of test effort spent on regression testing
Answer: B
NO.10 What is the main reason why reviews are especially beneficial in the above-mentioned scenario? 2
credits
A. They ensure a common understanding of the product.
B. They find defects early.
C. They enhance project communication.
D. They can be performed without exercising the code.
Answer: D