EXIN EX0-115 (IT Service Management Foundation based on ISO/IEC 20000)인증시험을 어떻게 준비하면 될가 아직도 고민하고 계시죠? 학원에 등록하자니 시간도 없고 돈도 많이 들고 쉽게 엄두가 나지 않는거죠? Pass4Test제품을 구매하신다면 그런 부담을 이제 끝입니다. Pass4Test덤프는 더욱 가까지 여러분들께 다가가기 위하여 그 어느 덤프판매 사이트보다 더욱 저렴한 가격으로 여러분들을 맞이하고 있습니다. EXIN EX0-115 (IT Service Management Foundation based on ISO/IEC 20000)덤프는 Pas s4Test제품이 최고랍니다.
NO.1 Which process includes the responsibility of recovering the service as quickly as possible?
A. Availability Management
B. IT Service Continuity Management
C. Incident management
D. Problem Management
Answer: C
NO.2 What would increase the amount of detail in the Configuration Management Database (CMDB)?
A. Increasing the scope of the CMDB
B. Increasing the number of attributes of each Configuration Item (CI) in the CMDB
C. Increasing the number of records in the CMDB
D. Increasing the use of the CMDB
Answer: B
NO.3 Different types of events are reported to the Service Desk. Which event is an incident?
A. Information about the rollout of a specific application
B. A notification that a new toner cartridge has just been installed in a printer
C. A report that the printer is not working
D. A request for the installation of a new bookkeeping package
Answer: C
NO.4 In recent months at a transport company with 1500 desktops, dozens of requests have been received
for expansion of the internal memory because its size has proven to be insufficient.
Which process should have prevented this from happening?
A. Capacity Management
B. Service Level Management
C. Configuration Management
D. Availability Management
Answer: A
NO.5 What is known as a temporary solution that enables the user to continue working?
A. Known Error
B. Request For Change (RFC)
C. Service Request
D. Workaround
Answer: D
NO.6 What is a Configuration Baseline?
A. A benchmark of the service provider's capability
B. A configuration audit report
C. A snapshot of the state of an IT Service or individual Configuration Item (CI) at a point in time
D. The change requests allocated to a release
Answer: C
NO.7 What has to be included in a well defined process?
A. Expected outcomes
B. Functions
C. Statistical support
D. Timelines
Answer: A
NO.8 Through which process does the implementation of new or changed services, including closure of a
service, need to be planned and approved.?
A. Business Relationship Management
B. Change Management
C. Release Management
D. Service Level Management
Answer: B
NO.9 Deming proposed a system of continuous improvement.
Which four activities does this system involve?
A. Plan. Do. Check and Act
B. Plan. Do. Evaluate and Act
C. Plan. Perform. Audit and Improve
D. Plan. Perform. Evaluate and Act
Answer: A
NO.10 One of the activities of Problem Management is the analysis of historical Incident and Problem data held
in the Configuration Management Database (CMDB) in order to understand trends.
Which aspect of Problem Management accomplishes this?
A. Error Control
B. Identification of root causes
C. Proactive Problem Management
D. Problem Control
Answer: C
NO.11 Quality Management Systems can assist organizations in enhancing what?
A. Customer satisfaction
B. ISO/EC 20000
C. Relationship with third parties
D. Supplier satisfaction
Answer: A