Pass4Test는 IT인증자격증을 취득하려는 IT업계 인사들의 검증으로 크나큰 인지도를 가지게 되었습니다. 믿고 애용해주신 분들께 감사의 인사를 드립니다. CompTIA SK0-003 (CompTIA Server+ Certification Exam) 덤프도 다른 과목 덤프자료처럼 적중율 좋고 통과율이 장난이 아닙니다.CompTIA SK0-003 (CompTIA Server+ Certification Exam)  덤프를 구매하시면 퍼펙트한 구매후 서비스까지 제공해드려 고객님이 보유한 덤프가 항상 시장에서 가장 최신버전임을 약속해드립니다. CompTIA SK0-003 (CompTIA Server+ Certification Exam) 덤프만 구매하신다면 자격증 취득이 쉬워져 고객님의 밝은 미래를 예약한것과 같습니다.




NO.1 A stripe set of maximum size is to be configured using two physical disks.
One disk has 150GB and the

other has 250GB in unallocated space. Which of the
following will be the size of the stripe set.?

A. 150GB

B. 300GB

C.
400GB

D. 500GB

Answer: B



NO.2 Which of the following technologies
allows multiple logical subnets to span an entire physical
switched

network?

A. ARP

B. DMZ

C. VLAN

D. VPN

Answer:
C



NO.3 A technician has a current baseline and is told to install
additional memory and a faster NIC card. At

which point in time should the
next baseline be run?

A. After the memory is installed

B. Before the
upgrade is performed

C. After the NIC is installed

D. After the upgrades
are performed

Answer: D



NO.4 Which of the following BEST describes how
server virtualization can cut down IT costs?

A. Server virtualization
increases server application performance allowing productivity to be
increased.

B. Server virtualization simplifies server administration and
reduces the IT department staffing needs.

C. Server virtualization implements
higher security measures at the server OS level reducing the need for

other
security implementations.

D. Server virtualization is a more efficient use of
hardware for multiple servers reducing the resource

utilization.

Answer:
D



NO.5 Users report that they are unable to connect to a server. An
administrator confirms that it is unreachable

across the network. Other
administrators have been working in the server room throughout the day.

Which
of the following is the NEXT step the administrator should take?

A. Verify
the configuration of the connected port on the network switch.

B. Reboot the
server.

C. Install a new NIC on the server.

D. Verify that network cables
are connected.

Answer: D



NO.6 Which of the following must be done to
properly conduct testing of the data backup portion of a disaster

recovery
plan?

A. Perform an integrity test of backup media.

B. Verify data on
backup media can be read.

C. Verify that backups have occurred and were
successful via the logs.

D. Restore backed up data to a test
server.

Answer: D



NO.7 Which of the following is the BEST recovery
method for a server that only aggregates report data and

stores data on
separate servers?

A. Full

B. Disk imaging

C. Incremental

D. Tape
backup

Answer: B



NO.8 Which of the following would be an advantage to
using a blade server as opposed to a rack mount

server?

A. Blade servers
allow for internal tape drives

B. Blade servers offer more rack density

C.
Blade servers are typically faster

D. Blade servers allow for more
RAM

Answer: B