VMware Certified Professional VCPC510시험은 중요한 IT인증자격증을 취득하는 필수시험과목입니다. VMware Certified Professional VCPC510시험을 통과해야만 자격증 취득이 가능합니다.자격증을 많이 취득하면 자신의 경쟁율을 높여 다른능력자에 의해 대체되는 일은 면할수 있습니다.Pass4Test에서는 VMware Certified Professional VCPC510시험대비덤프를 출시하여 여러분이 IT업계에서 더 높은 자리에 오르도록 도움드립니다. 편한 덤프공부로 멋진 IT전문가의 꿈을 이루세요.
NO.1 Which two components are required for a vCloud infrastructure installation? (Choose two.)
A. AMQP Broker
B. vCloud Connector
C. vShield Manager
D. Oracle/MS SQL database
Answer: C,D
NO.2 Which three features are only available when using a vSphere Distributed Switch? (Choose
three.)
A. Port Mirroring
B. PVLAN tagging
C. Egress Traffic Shaping
D. Ingress Traffic Shaping
E. 802.1q VLAN Tagging
Answer: A,B,D
NO.3 As a System Administrator you can disable an Organization vDC. Disabling will have which of
the
following effects? (Choose two)
A. vApps in the Org vDC that are not running cannot be powered on.
B. All vApps in the Org vDC will be shutdown.
C. Users will not be able to create or start additional vApps in that Org vDC.
D. The running vApps in the Org vDC will have their storage lease reset.
Answer: A,C
NO.4 An administrator attempts to delete the network named Internet but receives an error.
What is a possible reason for the error?
A. The network named Internet is backed by a port group on a vSphere Standard Switch.
B. The vShield Edge appliance on the external network is powered off.
C. The administrator needs to be an Organization Administrator.
D. The network is still in use by an Organization.
Answer: D
NO.5 An administrator would like to have vCenter take action any time a virtual machine is using
over
90% of its available resources for five minutes or longer.
Which three actions can be taken by vCenter Server in response to the trigger without running a
script? (Choose three.)
A. Power on a VM
B. Reboot Guest on VM
C. Increase Virtual Machine Memory
D. Migrate a VM
E. Increase Virtual Machine CPU Shares
Answer: A,B,D
NO.6 On which two vSphere elements can traffic shaping be configured? (Choose two.)
A. On a vSphere Distributed Switch dvPort for inbound and/or outbound traffic
B. On a vSphere Distributed Switch for inbound and/or outbound traffic
C. On a vSphere Standard Switch port group or the entire vSwitch for inbound traffic
D. On a vSphere Standard Switch port group or the entire vSwitch for inbound and outbound traffic
Answer: A,B
NO.7 Which two resources must be in place prior to creating a new Provider vDC? (Choose two.)
A. vCloud External Network
B. vCenter Datastore
C. vCenter Resource Pool
D. vShield Protection Group
Answer: B,C
NO.8 In a large organization, a user has 10 VMs deployed in vCloud Director, backed by a
Pay-As-You-
Go allocation model. The user needs to determine the charges being incurred for resource usage.
Which report type does the user need?
A. Showback Report
B. Usage Report
C. Cost Comparison Report
D. Cost Report
Answer: D