여러분은  IBM Certified Deployment Professional 000-570   인증시험 패스로 이 치열한 IT업계경쟁 속에서 자기만의 자리를 잡고, 스펙을 쌓고, 전문적인 지식을 높이고 싶으십니까?   IBM Certified Deployment Professional 000-570   패스는 쉬운 일이 아닌걸 알고 있습니다. IBM Certified Deployment Professional 000-570  패스는 여러분이 IT업계에 한발작 더 가까워졌다는걸 의미합니다.하지만 이렇게 중요한 시험이라고 많은 시간과 정력을 낭비할 필요는 없습니다. Pass4Test의 완벽한 자료만으로도 가능합니다.Pass4Test에서는 이미   IBM Certi fied Deployment Professional 000-570  인증시험의 일부 문제와 답을 사이트에 올려놓았으니 체험해보실 수 있습니다. Pass4Test 의  IBM Certified Deployment Professional 000-570   덤프에 신뢰가 갈 것이며 또 망설임 없이 선택하게 될 것입니다.  Pass4Test  덤프로 여러분은 한번에 시험을 패스할 수 있으며 또 개인시간도 절약하고 무엇보다도 금전상으로 절약이 제일 크다고 봅니다.

 

 

NO.1 What does an active workflow process define?
A. The flow of work in Application Designer
B. The process to add an attribute to an application
C. The different work to be performed by the lead craft
D. The different paths that a record can take as it moves through a business process
Answer: C

NO.2 A company has deployed IBM Maximo Asset Management V7.5 (Maximo) to manage the company
assets and the purchasing process. The company's purchasing process does not require an approved
purchase request (PR) in order to generate a new purchase order (PO) but the buyer reported this
problem when trying to create a new PO from an unapproved PR:
Where can this validation be turned off in Maximo?
A. Organizations application
B. Purchase Orders application
C. System Properties application
D. Database Configuration application
Answer: A

NO.3 What is the purpose of commodity codes?
A. To group like items for issue
B. To group like items for purchasing
C. To group like items for classification
D. To group like items for asset bill of material
Answer: B

NO.4 Which statement is true to review the content of a scheduled report?
A. Use the Report Administration application to view and select from a list of report outputs
B. Use the Report Administration application to choose the correct report and then click the View button
C. Use the URL from the link supplied in the e-mail to access a PDF file served up directly by the HTTP
server
D. Access the URL from the link supplied in the e-mail and then log into Maximo and select the Download
Content button
Answer: D

NO.5 Which standard relationship is the container relationship for assets?
A. BACKUPS
B. INCLUDES
C. CONNECTS
D. INTERSECTS
Answer: B

NO.6 An asset is created and measurement points are associated. Which IBM Maximo Asset Management
V7.5 application sets Upper Limit and Lower Limit Job Plans?
A. Meters
B. Assets
C. Condition Monitoring
D. Work Order Tracking
Answer: C

NO.7 What are two uses for the Assignment Manager application? (Choose two.)
A. To dispatch labor and schedule work for an organization
B. To create and manage work orders for assets and locations
C. To report labor transactions by labor, by vendor/contract, by work order, or by ticket
D. To specify which organizations and sites can use the information that is on the job plan and its tasks
E. To view the requirements that were created from the work plan as well as the unplanned work on a
work order
Answer: A,E

NO.8 If the Integrity Checker utility tool reports that some groups have no privileges in the Maximo security
tables, how could this be resolved?
A. Run the integrity checker in repair mode
B. Run the integrity checker in backup mode
C. Create a new Maximo Security group for the Maximo security tables and run the Integrity Checker
utility again
D. Create a new security group with all grants on the Maximo security tables and run the Integrity Checker
utility again
Answer: A

NO.9 When creating a purchase request line by using the Select Spare Parts button, refined search is
allowed by specifying at least one of which two data fields? (Choose two.)
A. Site ID
B. Description
C. Item Number
D. Asset Number
E. Organization ID
Answer: A,D

NO.10 What is the definition of a work package?
A. It groups existing work orders under a new parent work order.
B. It is a preventive maintenance work order hierarchy that has been created from a route.
C. It is a work order linked to all the originating services requests for the work order and is created from
the Related Records tab.
D. It is a group of work orders in Waiting to be Scheduled status that are the responsibility of one person
and is created in the Assignment Manager application.
Answer: A

NO.11 A forecast for a preventive maintenance record has been generated. How can the forecast date be
adjusted from the Preventive Maintenance application?
A. From the Forecast tab, select a forecast row, enter a value in the New Date field, click Save
B. From the Select Action menu, select Generate Forecast, enter a value in the Forecast Days field, click
OK
C. From the Frequency tab, select the Time Based Frequency tab, enter a value in the Frequency field,
click Save
D. From the Frequency tab, select the Time Based Frequency tab, enter a value in the Extended Date
field, click Save
Answer: A

NO.12 After fully receiving a shipment it is discovered that the item or tool has been received incorrectly. How
can a receipt be reversed from the Shipment Receiving application?
A. Find the shipment receipt, change the status to VOID from the Select Action menu, click Save
B. Find the shipment receipt, click the checkbox Void Receipt for each line to be reversed, click Save
C. Find the shipment receipt, click the button Select Receipt to Void, select each line to be voided, click
OK
D. Find the shipment receipt, click the button Select Records to Void, select each line to be voided, click
OK
Answer: D

NO.13 Which property is used to define the directory used when importing data using the Integration
Framework?
A. Mxe.int.dir
B. Mxe.int.localdir
C. Mxe.int.globaldir
D. Mxe.int.accessdir
Answer: C

NO.14 In the Receiving application, what does the Quantity Accepted field indicate?
A. The quantity of items that passed inspection
B. The quantity of items accepted for inspection
C. The quantity of items that received inspection
D. The quantity of items that are awaiting inspection
Answer: A

NO.15 What does the Enable Repair Facilities Organization option allow?
A. Creating a work order in a site different from the site of the asset on that work order
B. Reserving items from one site to use at another site on an emergency maintenance work order
C. Moving an asset from one location to another location on an emergency maintenance work order
D. Creating a preventive maintenance (PM) record in a site different from the site of the asset on that PM
Answer: A

NO.16 Which function is performed in the Quick Reporting application?
A. Create failure code hierarchies
B. Create job plans and safety plans
C. Create preventive maintenance schedules
D. Report actual labor, materials, and tools used in the work
Answer: D

NO.17 Which IBM Maximo Asset Management location status is necessary to associate a location with a
system.?
A. Active
B. Ready
C. Operating
D. Decommissioned
Answer: C

NO.18 What comprises a failure code?
A. Failure, affect, fix
B. Issue, reason, resolution
C. Problem, cause, remedy
D. Situation, impact, solution
Answer: D

NO.19 A customer has an escalation that requires notifications to go to both Marie Smith and her supervisor
Lee Tsumi. How can both users be included as recipients on a communication template?
A. Create a role for both Marie and Lee
B. Create a Person Group with Marie as the primary
C. Add both e-mail addresses on the Recipients tab
D. Include both user e-mails in the Recipient field separated by a colon
Answer: C

NO.20 Which method is used to view labor hours, costs, and material costs for a particular work order?
A. from the Work Order Tracking application, select the Cost tab
B. from the Work Order Tracking application, go to the Select Action menu and select View > Costs
C. from the Actuals tab of Work Order Tracking application, download and summarize each of the table
windows for Labor, Materials. Services, and Tools
D. navigate to the Cost Management application, query for the work order in question to view estimated
and actual hours and costs for labor in addition to estimated and actual costs for materials and service
Answer: B
Posted 2012/12/7 6:33:28  |  Category: 미분류  |  Tag: