IT인증,IT자격증,IT자격증시험,IT인증시험

http://www.pass4test.net/

Exin Certification PR2F덤프데모

Exin Certification PR2F시험을 한방에 편하게 통과하여 자격증을 취득하려면 시험전 공부가이드가 필수입니다. Pass4Test에서 연구제작한 Exin Certification PR2F덤프는Exin Certification PR2F시험을 패스하는데 가장 좋은 시험준비 Exin Certification PR2F공부자료입니다. Pass4Test덤프공부자료는 엘리트한 IT전문자들이 자신의 노하우와 경험으로 최선을 다해 연구제작한 결과물입니다.IT인증자격증을 취득하려는 분들의 곁은   Pass4Test가 지켜드립니다.







NO.1 Which statement is FALSE?

A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit

B. A project's output is any of the project's specialist products

C. A project benefit is only realized after the project has closed

D. A project outcome is the result of the change derived from using the project's outputs

Answer: C




NO.2 Which of the following is NOT part of quality planning?

A. Define quality responsibilities

B. Gain acceptance of the project product

C. Agree acceptance criteria

D. Set quality tolerances

Answer: B




NO.3 Which task is performed by the Change Authority?

A. Set a change budget

B. Approve or reject a request for change within approved limits

C. Refer changes that exceed budgetary limits to the Project Manager for approval

D. Update the configuration management system when a change is approved

Answer: B




NO.4 Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier

environment?

A. Specify the desired result

B. Provide the resources and skills to deliver the desired result

C. Pay for the project

D. Specify the benefits of the project

Answer: B




NO.5 In what product should the quality criteria for a specialist product be recorded?

A. Quality Management Strategy

B. Quality Register

C. Product Description

D. Project Product Description

Answer: C




NO.6 What is the first task of product-based planning?

A. Produce the Initiation Stage Plan

B. Write the Project Product Description

C. Identify dependencies

D. Create the product breakdown structure

Answer: B

Posted 2014/7/29 10:49:19  |  Category: EXIN  |  Tag: PR2F덤프데모