IT인증,IT자격증,IT자격증시험,IT인증시험

http://www.pass4test.net/

EMC E20-017 (Information Availability Design Specialist Exam for Data Center Architects)덤프공부

Pass4Test의 EMC E20-017 (Information Availability Design Specialist Exam for Data Center Archit ects)덤프가 있으면 힘든 EMC E20-017 (Information Availability Design Specialist Exam for Data Center Architects)시험이 쉬어져서 자격증을 제일 빠른 시간내에 취득할수 있습니다.제일 어려운 시험을 제일 간단한 방법으로 패스하는 방법은 Pass4Test의  EMC E20-017 (Information Availability Desig n Specialist Exam for Data Center Architects)덤프로 시험준비 공부를 하는것입니다.

 

 

NO.1 A company has estimated a cost of $220,000 to build its new data center. The new data center will
serve an additional 20,000 clients for which the company will gain $30,000 per month. In addition, the
company has agreed to spend $1,000 every month in support costs.
In order to achieve a break-even point, what is the minimum time period the data center must be
operational?
A. 8 months
B. 9 months
C. 10 months
D. 11 months
Answer: A

NO.2 In the context of "establishing information availability," what is an operation management activity?
A. Capacity planning
B. Data classification
C. Testing
D. Implementation planning
Answer: A

NO.3 A company has a shared pre-staged infrastructure at an alternate site. This approach enables the
company to rebuild systems and applications in the event of a disaster.
What is the term for this strategy?
A. Hot site
B. Manual failover site
C. Cold site
D. Warm site
Answer: A

NO.4 A company's IT department is comparing two technology proposals. Option 1 would retain legacy
equipment while Option 2 would replace the existing equipment with a new one.
Option 1:
-Total operation costs = $400,000 per year -Annual storage requirements = $100,000 per year
Option 2:
-Initial investment = $1,250,000 -Recurring annual operation costs = $150,000 per year -Annual storage
requirements = $100,000 per year
The company's write-off costs for the legacy equipment is $50,000. As a business analyst using a TCO
analysis, which option would you recommend?
A. Option 1 is feasible if the project lifespan is less than 5 years
B. Option 1 is feasible if the project lifespan is more than 6 years
C. Options 1 and 2 are feasible if the project lifespan is 5 years
D. Option 2 is feasible if the project lifespan is less than 5 years
Answer: A

NO.5 A company has estimated a cost of $240,000 to build its new data center. The new data center will
serve an additional 20,000 clients for which the company will gain $35,000 per month. In addition, the
company has agreed to spend $2,000 every month in support costs.
In order to achieve a break-even point, what is the minimum time period the data center must be
operational?
A. 8 months
B. 9 months
C. 10 months
D. 11 months
Answer: A

NO.6 In which focus area of the Information Availability Design Framework can seamless movement of data
between tiers of storage be found?
A. Automate
B. Create Copies
C. Distribute
D. Store
Answer: A

NO.7 As represented in the exhibit, a company has a system with three critical components.
Each component must be functioning for the system to be operational. SLAs have been established
between the business and IT that define normal hours of operations for service as 8 A.M. - 8 P.M.,
Monday through Friday.
What is the availability (percentage) of Component 1?
A. 78
B. 81.7
C. 89
D. 91.7
Answer: B

NO.8 In which focus area of the Information Availability Design Framework can platform integrity be found?
A. Store
B. Automate
C. Create copies
D. Distribute
Answer: A

NO.9 As represented in the exhibit, a company has a system with three critical components. Each component
must be functioning for the system to be operational.
What is the scheduled availability (percentage) for the system?
A. 84
B. 86
C. 88
D. 90
Answer: C

NO.10 The exhibit represents the expected financial results of a storage technology investment.
What does the ® ¯: represent?
A. Cost of investment equals the gain from the investment
B. Asset exceeds liability
C. Deployment cost crosses the planned deployment time
D. Return on investment
Answer: A

NO.11 A company wants to replace its physical tape library with a virtual tape library (VTL). To deploy the VTL,
the company spends $300,000 for the hardware costs and $50,000 for the implementation charges.
Once the data is migrated from the physical tape library to the VTL, the physical tape library will be
decommissioned for a cost of $50,000. The company will gain $70,000 per month due to this VTL
implementation.
What is the return on investment (ROI) in one year and the break-even point for the company ¯:s initial
investment?
A. 85%; Month 8
B. 85%; Month 9
C. 110%; Month 6
D. 110%; Month 8
Answer: C

NO.12 A company has a system with three critical components as represented in the exhibit.
Each component must be functioning for the system to be operational. Following an outage, certain
components seem to take longer to restore back to service than others.
What is the mean time to repair (MTTR) for Component 3?
A. 2 hours
B. 3 hours
C. 5 hours
D. 10 hours
Answer: C

NO.13 Based on strategic plans regarding green initiatives, an IT department is considering server
consolidation in its data centers.
Which set of elements should be included in the business value analysis to maximize the ROI for such an
initiative?
A. Asset utilization, recovery of stranded assets, and cost of floor space and power
B. Productivity of staff, response to business conditions, and utilization of storage
C. Asset utilization, backup costs, and need for availability
D. Cost of floor space and power, FTE-managed TB of storage, and reduction in SLA penalties
Answer: A

NO.14 A company wants to replace its physical tape library with a virtual tape library (VTL). To deploy the VTL,
the company spends $300,000 for the hardware costs and $60,000 for the implementation charges. Once
the data is migrated from the physical tape library to the VTL, the physical tape library will be
decommissioned for a cost of $50,000. The company will gain $60,000 per month due to this VTL
implementation.
What is the return on investment (ROI) in one year and the break-even point for the company ¯:s initial
investment?
A. 35%; Month 6
B. 35%; Month 7
C. 76%; Month 6
D. 76%; Month 7
Answer: D

NO.15 The exhibit represents a Component Failure Impact Analysis (CFIA) for a company's IT infrastructure.
Several Requests for Change (RFC) were raised.
Which RFC should be considered a priority for implementation?
A. Deploying a switch architecture with no single point of failure
B. Clustering the backup server with multiple storage devices
C. Configuring the NAS device in an active-active mode
D. Adding more disk drives to the storage array
Answer: A
 
Posted 2013/7/18 6:44:16  |  Category: 미분류  |  Tag: