IBM Certified BPM Program Manager A2180-188시험을 통과하여 자격증을 취득하여 IT 업계에서의 자신의 자리를 지키려면 많은 노력이 필요합니다. 회사일도 바쁜데 시험공부까지 스트레스가 장난아니게 싸이고 몸도 많이 상하겠죠. Pass4Test는 여러분을 위해 최신 IBM Certified BPM Program Manager A2180-188시험에 대비한 IBM Certified BPM Program Manager A2180-188덤프를 발췌하였습니다. IBM Certified BPM Program Manager A2180-188덤프는 IBM Certified BPM Program Manager A2180-188시험의 기출문제와 예상문제가 묶어져 있어 시험적중율이 굉장히 높습니다. 쉽게 시험을 통과하려면 Pass4Test의 IBM Certified BPM Program Manager A2180-188덤프를 추천합니다.
NO.1 The BPM Program Manager, Process Owner, and Lead Developer are collaborating to
define the theme
and assign user stories for the next iteration. The team is planning the 7th of 15 iterations in
the Release
Plan for Release One. The Program Manager displays a Team Velocity chart showing that
the
Development team has shown significant growth in story points accepted from iterations 1 to
4 and has
been leveling off to roughly 200 story points in iterations 5 and 6.
Given there are 9 iterations remaining in the release plan, the Process Owner immediately
recognizes
there is room for roughly 1800 story points in the remaining time for Release One. However,
the backlog
contains 2400 story points marked as "high" priority and another 1200 story points marked as
"medium"
priority. The Process Owner asks to reduce the points assessed to the high priority user
stories to bring
the total points down to roughly 1800 so as to make them fit in the remaining time. The
Program Manager
agrees.
What is wrong with this scenario.?
A. This is a conversation for a Release Planning meeting and not during Iteration Planning.
B. Team Velocity is fixed and changing the method of estimating story points mid-way
through a release
will not increase the scope of work that can be completed.
C. Process Owner forgot to include a risk factor of 1.4 that should be applied to 1800
resulting in roughly
2500 story points (1.4 x 1800 = 2520) remaining in the Release. No action should be taken.
D. Both "high" and "medium" priority stories should be included in the Release Plan meaning
all user story
points should be reduced by 50% to get all high/medium priority stories to fit in 1800 points
remaining
(2400+1200 = 3600 : 3600/2 = 1800).
Answer: B
NO.2 It is discovered while running Playback 0 that an important but not strictly necessary
sub-process was
missed in the analysis. How should the program manager recommend handling the missed
sub-process?
A. Redo Playback 0 and include the sub process.
B. Note the sub-process as a user story and save it for the next release.
C. Include the sub-process in Playback 1 without validating with the process owner.
D. Schedule a special iteration and playback to address the sub-process after Playback 3.
Answer: B
NO.3 The BPM program manager and process owner for a new hire onboarding process
project need to
ensure that the solution developed by the team will be accepted and adopted by the target
users. To
facilitate this, they decide to:
A. plan additional playbacks for user screens.
B. agree with users to postpone the release until every feature is correct.
C. involve champion SMEs in the discovery and implementation including playbacks.
D. insist on documentation of all user requirements before having the development team
begin work.
Answer: C